Project Overview

The Sydney West project involved the upgrade of the 132kV and 330kV SSB replacement works. This included upgrade of cable ducts in yard, cable replacement and equipment replacement.

Project Description

Our responsibility was installation of storm water drainage, concrete ducting for high voltage cables, as well as installation of all cable trenching for 330kV yard and 132kV yard.

Client

Zinfra

Asset Owner

Transgrid

Duration

9 months

Capabilities
Concrete Structures
Electrical